Days 8 and 9 dealt with the electrical and HVAC subs making sure we would be properly juiced and heated. There isn't much in the way of pictures because, well frankly, it's just not that interesting.
We decided to go with mainly can lights because we do not have the luxory of high ceilings in the basement and Jeff did not want to feel like he had to stoop when he walked down there. Here are the cans for the TV area.
Here are the cans for the exercise area.
Remember that fresh air intake I told you they would need to move? I think this is where it is going.
Here is the ventilation for the bathroom.
There is still a little more HVAC work to be done and the cable guy will be here on Tuesday. Hopefully, the inspection will also be done on Tuesday and then the drywall starts going up on Wednesday.